Certified Construction Contract Administrator Exam

Sample Questions



1.	Construction Contract Administration begins:
	A.	When the contract documents are issued for bid or negotiation.
	B.	When the owner-contractor agreement is executed.
	C.	When construction commences.
	D.	During the contract documents phase of the A/E's services.

2.	The duties, responsibilities, and limitations of authority of the owner, A/E and 
	contractor may be found in which of the following:
	A.	Conditions of the contract.
	B.	Technical specifications.
	C.	Notice to Proceed.
	D.	Drawings.

3.	Project delivery systems include:
	A.	Cost-Plus-Fee Contract.
	B.	Negotiated Contract.
	C.	Stipulate Lump Sum Contract.
	D.	Owner-Builder Contract.

4.	Pre-construction submittals include:
	A.	Bonds and Insurance Certificates.
	B.	Executed Agreement.
	C.	Samples and Mockups.
	D.	Shop Drawings and Product Data.

5.	AIA and EJCDC general conditions require submittals to be reviewed by:
	A.	Contractor.
	B.	A/E.
	C.	Owner.
	D.	Contractor and A/E.

6.	A construction progress meeting is:
	A.	A regularly scheduled gathering.
	B.	A meeting between contractor and subcontractors.
	C.	Addresses bid items.
	D.	A meeting between subcontractor and suppliers to discuss delivery of 	
		materials.

7.	The A/E project representative is usually not empowered to:
	A.	Observe progress and quality of work.
	B.	Monitor construction progress schedule.
	C.	Review contract documents with contractor's superintendent
	D.	Act on behalf of A/E.


8.	Upon discovery of a discrepancy within the contract documents, the standard 
	conditions of contract state that the contractor shall:
	A.	Interpret documents and act accordingly.
	B.	Report errors, inconsistencies, or omissions to A/E.
	C.	Price the most expensive option.
	D.	Inform the affected subcontractor.

9.	The Date of Commencement of work is date stipulated in the:
	A.	Bid Form.
	B.	Supplementary Conditions.
	C.	Summary of Work.
	D.	Owner-Contractor Agreement.

10.	A written request for an adjustment in the contract amount or time is a:
	A.	Demand for Arbitration.
	B.	Claim.
	C.	Dispute.
	D.	Change Order.

11.	Requirement for allowing modifications to the contract documents are addressed 
	in:
	A.	Conditions of contract.
	B.	Division 1 - General Requirements.
	C.	Bidding requirements.
	D.	Both A and B.

12.	Which of the following combinations of documents establishes the 
                responsibilities of the owner, A/E, and contractor for measurement and payment:
	A.	General conditions and payment bond.
	B.	General conditions, payment bond and Division 1 General Requirement, 	
		Section 01025 - Measurement and Payment.
	C.	Owner - A/E agreement and general conditions.
	D.	Owner - A/E agreement, general conditions, and payment bond.

13.	Authorities having jurisdiction:
	A.	Insure defective work does not occur.
	B.	Effect quality by adopting and enforcing minimum requirements.
	C.	Perform all testing and inspection.
	D.	Are enforcement agents hired by the owner.

14.	Scheduling and coordination of systems startup should be specified in:
	A.	General conditions of the contract.
	B.	Division 1 general requirements.
	C.	Individual specifications in Divisions 2 through 16.
	D.	General conditions of the contract and Division 1 general requirements.